MRT Phase 1 Project A Section

Published:2019-10-08 17:44:00

Project Scope: 2.7km double-line shield tunnel, museum underground station, North Portal comprehensive building, central wind shaft, 8 communication channels, LRT light rail station underground pile foundation replacement, related electromechanical and building installation engineering, etc.

Duration: from August 1st, 2012 to November 30th, 2016. 52 months.

Contract sum: USD 216 million